Crackley Lane road closure: Monday 27th May - Friday 21st June
From Monday 27th May - Friday 21st June, Crackley Lane will be closed between the Cryfield Grange Road junction - Bockendon Road. For further information, please visit .
A46 Mainline Lane 1 Closure – A46 Mainline Lane 1 Closure both North and South bound: Wednesday 24th April to Sunday 11th August 2024
On the morning of Wednesday 24th April 2024 the A46 will be reduce to two lanes between Stonebridge Highway Junction(Thickthorn) and the Kenilworth Road Junction (Stivichall). This is to allow the scheme to progress safely while contractors is working in the verges. The lane closures will remain in place until the evening of Sunday 11th August 2024. Due to the reduction in road capacity please expect delays during peak times. Full overnight closures will be in place over the first two nights and final two nights to allow the safe installation of the traffic management, a signed diversion will be in place for the full closures.
In addition to these works, HS2 are constructing the A46 Box structure and will complete preparatory works by installing traffic management on the A46 between Thickthorn roundabout and A45 Stivichall Interchange. This traffic management is a combination of lane restrictions and overnight carriageway closures between May and October followed by a closure in early 2025 to install the new structure. For more details please visit
UPDATE (07/03/2024): Existing Bridge Closure – Stoneleigh Road Closure between A46 slip roads from Monday 11th March to Sunday 17th March 2024
From Monday 11th March 2024 (originally 4th March), Stoneleigh Road will be closed between the two A46 slip roads to allow the safe installation of new lighting columns as part of the bridge improvement works. The closure is scheduled to remain in place until the evening of Sunday 17th March 2024. For further information please visit the scheme website: